In aluminum billet melting-casting lines, violent liquid-level disturbance caused by rotor stirring is a major trigger for slag entrapment. Severe turbulence submerges surface oxide slag into molten aluminum, generating inclusion defects inside billets and impairing downstream extrusion performance.
Conventional degassing units may suffer mechanical vibration caused by poor drive-shaft concentricity or improper rotor immersion depth, which amplifies liquid-level fluctuation. For high-throughput billet lines running at 25–35 t/h, stable melt operating condition is essential to mitigate slag inclusions.
The FDUII-30 fixed box-type dual-rotor degassing unit features a chamber optimized via water-simulation test. Combined with dual variable-frequency rotors and submerged inlet-outlet design, the unit implements melt degassing while restraining intense liquid-level movement to lower slag entrapment risk, matching non-stop continuous casting rhythm for aluminum billet production.
| Molten aluminum throughput | 25–35 t/h |
|---|---|
| Number of rotors | 2 composite graphite rotors |
| Rotor speed range | 0–600 rpm, variable-frequency control |
| Rotor immersion depth in melt | 600–700 mm |
| Drive-shaft concentricity deviation | ≤0.5 mm |
| Max melt depth inside chamber | 750 mm |
| Molten aluminum operating temperature | 680–770 ℃ |
| Temperature control accuracy | ±2 ℃ |
Beyond precise rotor assembly, submerged inlet-outlet ports isolate ambient air and cut down oxide dross generation. Dual-chamber layout supports even inert-gas bubble distribution and weakens local turbulent flow.
Lubrication and cooling modules are equipped for rotor driving assembly to sustain smooth long-time operation. Inert gas ports on tank cover feed N₂ or Ar to suppress fresh dross formation. Hydraulic lifting-rotation mechanism enables routine inspection and rotor replacement, preventing abnormal stirring from worn rotor components.
Hardware configuration alone cannot fully eliminate slag-related issues. Operators shall set rotor immersion depth and rotating speed according to real-world production throughput, and regularly inspect drive-shaft concentricity.
Important: This equipment mitigates slag entrapment risk yet cannot remove foreign slag carried over from upstream processes, so pre-filtration and pre-slag-removal procedures remain necessary.